The professional football field project of Jinan Yellow River Sports Center has reached a major engineering milestone – the hoisting operation of the spoke-type cable truss has been fully launched, marking that the project construction has officially entered a new stage.
The professional football field project of Jinan Yellow River Sports Center has reached a major engineering milestone – the hoisting operation of the spoke-type cable truss has been fully launched, marking that the project construction has officially entered a new stage

The Yellow River Sports Center is located in the Cuizhai area of the Jinan New and Old Kinetic Energy Conversion Pilot Zone, with a total construction area of approximately 197,300 square meters. As the first 60,000-seat professional football stadium in Shandong Province that meets the latest FIFA standards, this project has witnessed multiple industry breakthroughs from design to construction:
Structural record: The maximum cantilevered length of the roof steel structure reaches 45 meters, setting a domestic record for sports venues.
System innovation: Integrating rigid roofs with flexible cable-membrane structures, it has become the world’s first planar single-layer membrane spoke-type cable-membrane structure system.
Material leadership: For the first time in China, high-transparency PTFE mesh membranes have been widely applied on a large scale in professional football fields, combined with an irregular cable-membrane flexible system, presenting a complex and advanced large-span spatial structure.
Complex craftsmanship: It is regarded as one of the professional football fields with the highest construction difficulty in the country.
Yexing membrane structure
As the membrane structure professional contractor of this project, Yexing, according to the on-site information from the project manager, has successfully completed the assembly of all trusses and is currently advancing the truss installation work in an orderly manner.
The inner circle of the roof adopts a flexible cable-membrane structure system supported by spok-spoke cable trusses. The overall hoisting and lifting process uses the advanced technology of “low-altitude stress-free assembly → aerial traction lifting → high-altitude step-by-step synchronous tensioning”, and is equipped with a clustered hydraulic control system for cable lifting and tensioning.

The project has specially set up a centralized control room for the lifting of cable structures, enabling the synchronous lifting and tensioning of 48 axis cables to ensure precise and efficient construction.
According to the plan, after the hoisting of the spoke-type cable truss is completed, the construction of the high light transmittance field core membrane will be carried out immediately. The entire professional football stadium project is expected to be completed and delivered by the end of 2026. After its completion, this place will take football as the engine and the Yellow River as the bond to further promote the upgrading of the sports industry’s level, and help Jinan take big steps from the “Spring City Era” to the “Yellow River Era”.

Please look forward to the splendid opening of this sports landmark that embodies innovative technologies and the vision of The Times!